Thunder Cranes successfully and safely completed a challenging motor removal on an offshore platform’s gas compression module. To design and execute this job required a high degree of ingenuity, experience and expertise from the project leaders, engineers, and lifting specialist involved. It demonstrated the effectiveness of our zone 2 certified, self-lifting crane packages in delivering lifting solutions at a fraction of the cost of a barge crane.
An 18-ton gas lift compressor motor, located on COB-P1 platform offshore, was scheduled to be removed and transported onshore for refurbishment / overhaul. The motor was located on the 2nd level of the gas compression module – known as “Module A” – which was a steel framed structure located on the deck of the main platform.
Although the COB-P1 platform was equipped with cranes on both the West and East sides, each with a Safe Working Load capacity of 20 tons, these cranes were unable to perform the motor lift due to their insufficient lifting capacity at the required radius.
Given the high cost and limited availability of suitable barge cranes, our client NPE reached out to us to help design a more affordable and effective alternative. Thunder Cranes conducted site surveys and studies in the process of designing the proposed solution.
Challenges & Solutions
Key Challenges:
- Challenging Rig Up Location
- Space Constraints
- Gas Environment
- Heavy Lift – 18MT
Solutions:
- Multiple site surveys and studies were required before the methodology could be confirmed. Many aspects of the job – from rig up procedure, to equipment and materials – needed to be customised, or fabricated, specifically for this project.
- To carry out the critical lift, Thunder Cranes proposed the TC20 portable-modular stiffleg crane. We determined that the TC20 could be rigged up and positioned above the motor – on the top deck of Module B located adjacent to Module A – and so would then be in a position to lift the 18MT motor in a single lift from the platform to the supply vessel.
Modular Cranes
- TC05 & TC20 stiff leg cranes. Due to the insufficient reach radius of the platform crane, a TC05 crane would need to be employed as a rig-up assist crane for the TC20 and a new TC20 rig up sequence was designed specifically for this job.
Boom Length & Wire Rope
- The ideal TC20 boom length in this scenario was the 40ft boom since it would contain fewer parts, and be faster and easier to assemble in the limited space.
- As the 18MT lift required a 4-part reeve the TC20 winch was therefore re-spooled with 700ft of wire rope to cover the vertical distance of the lift (120ft).
Clamping System
- With no hot work permitted, we deployed our clamping & bolting systems to secure the crane base beams to the module structure.
- Custom built spacers were needed under the TC20 base beam due to obstructions (large pad eyes) which could not be removed and this in turn required the fabrication of longer stud bolts on the clamping system.
Zone 2 Powerpack
- To deal with the gas environment we provided Zone 2 certified diesel powerpacks as the prime movers for our hydraulically operated modular cranes.
Scaffolding
- In addition, with limited handrail and grated deck spaces on the top of Module B, scaffolding with work floors were needed to provide additional / temporary decking at the top of the module.
Rope Access & Specialised Rigging
- The motor was located underneath the top deck of Module A, and would need to be lifted out from the side of the structure, not through the top which was not possible without the removal / dismantling of beams, piping and/or process equipment.
- To bring the motor out though the side of the structure, our partners at NPE designed a customised extension beam and trolley system, which once installed, together with a customised rigging and load transfer system and a rope access technician, would enable a “hand off” of the suspended load from the beam and trolley to the TC20.
Steps/Sequence of Work
- TC & NPE crew mobilization offshore on 21 Nov, 2024 for site preparation works – removal of obstructions, erection of scaffolding, etc.
- TC05 & TC20 mobilization offshore to COB-P1 via supply vessel.
- TC05 & TC20 crane components lifted by platform crane from supply vessel to the first staging area on COB-P1.
- TC05 & TC20 crane components lifted by platform crane from staging area on COB-P1 to TC05 staging area on Module B.
- TC05 rig up supported by platform crane, followed by 3rd party inspection and load testing.
- TC20 rig up supported by TC05, followed by 3rd party inspection and load testing.
- NPE crew installation of extension beam and trolley
- Removal of motor through the side of Module A by NPE and transfer to TC20
- TC20 lowering motor to supply vessel on 21 Dec, 2024.
- Rig down and demobilisation of TC20 & TC05 and all rigging and lifting equipment
Outcome
The motor removal was successfully carried out on 21 December 2024. The total project timeline from rig up to rig down was just 30 days, excluding the mobilization to/from the Luanda supply base. Although several minor delays were experienced, the work was completed within the planned schedule.
The location, complexity, space constraints, and other aspects made this project one of the most challenging projects Thunder Cranes has been involved with to-date.
The project showcased the expertise, experience and teamwork of NPE & Thunder Cranes, and it also showcased the TC20 and TC05 stiff leg cranes and the unique factors that make our cranes built-to-deliver in demanding offshore environments.
Application
- Lifting Solution for Gas Lift Compressor Motor Offshore
Challenges
- Challenging Rig Up Location
- Space Constraints
- Gas Environment
- Heavy Lift – 18mt
Our Service
- Offshore Rental Crane TC20 & TC05
- Complex Rigging Solutions
- Crane Operators
- Detailed Planning & Preparation
Benefits
- Cost effective, safe, precision lifting solutions
Location
- Angola